SL NoName of the ContractPeriodCompleted Value
1Construction of 703.20 m. pre-stressed Bridge at 32nd km of Sylhet-Salutikor-Companygonj-Bholagonj under LGED, Sylhet2008Tk. 239.34 million
2Construction of 600.00 m. pre-stressed Bridge on cast-insitu pile (750mm dia) foundation under Construction of Road from Bastuhara Main Road to City Bypass Road2008Tk. 220.00 million
3Construction of Dhauk Bridge at 29th km of Panchagorh-Tetulia Road under Panchagorh Road Division2006Tk. 100.00 million
4Construction of Zakigonj Bridge under Zakigonj-Vingar bazaar-Laxmibazar-Dubagbazar Road, Contract Package No. Syl/UZR-522006Tk. 73.84 million
5Construction of 75.00 m. pre-stressed Bridge on cast-in-situ pile (900mm dia) foundation, RRMP-II, Widening Contract W3 (IDA Project).1996 - 1998Tk. 50.00 million
6Construction of Calender Hamilton Bridge 405ft (123.476m) at Khero, 58th mile of Dhaka-Mymensingh Road (ODA Grant Project) on Cast in Situ & Pre-cast piles1987 - 1989 Tk. 43.60 million
7

526’-0” long Balanced cantilever Bridge at Bhaluka on Dhaka– Mymensingh Road on well and cast-in-situ pile foundation.
1982 - 1985 Tk. 190.00 million
8240”-0” Long R.C.C. Phulpur Bridge on well foundation on Mymensingh- Haluaghat Road.1980 - 1982 Tk. 7.28 million
9300’-0” long Arpara Calender Hamilton Bridge (200’-0” single span) on Pre-cast pile foundation on Jessore-Magura Road.1980 - 1983 Tk. 7.68 million
10Construction of Ferry Approaches and Gangways on pile foundation on Barisal-Patuakhali Road1979Tk. 6.00 million
11Construction of Jetteye at Barisal on pile foundation1979Tk. 12.00 million
12205’-0” long Shimakali Calender Hamilton Bridge (single span) on Pre-cast pile foundation on Magura Road.1978 -19 80 Tk. 6.50 million
13250'-0” long Moukaran Acrow Panel Bridge with 130’-0” central span on well and pile foundation on Barisal-Patuakhali Road.1978 - 1982 Tk. 8.12 million
14Pre-stressed concrete Bridge on pile foundation on Joydevpur-Tangail Road.1976 - 1978 Tk. 22.00 million
15280’-0” long R.C.C. balanced cantilever Sherry Bridge on well & pile foundation on Jamalpur-Sherpur Road.1976 - 1978Tk. 5.00 million
16100’-0” long R.C.C. balanced Cantilever Parulia Bridge on well foundation on Satkhira-Betkhali Road.100’-0” long R.C.C. balanced Cantilever Parulia Bridge on well foundation on Satkhira-Betkhali Road.1974 - 1977 Tk. 2.00 million
17160’-0” long R.C.C. balanced cantilever Bridge on well foundation on Satkhira-Bhetkhali Road.1974 - 1976 Tk. 3.00 million
18160’-0” long R.C.C. balanced cantilever Kadamtala Bridge on Satkhira-Illispur Road.1974 - 1976 Tk. 4.00 million
19130’-0 long R.C.C balanced canti- lever Kaliganj Bridge on well and pile foundation on Jessore-Jhenaidah Road.1973 - 1976 Tk. 3.00 million
20185’-0” long R.C.C. balanced cantilever Kulia Bridge on well & pile foundation on Satkhira-Betkhali Road.1973 - 1975 Tk. 4.00 million
21160’-0” long R.C.C. balanced Cantilever Shambhuganj Bridge on pile foundation on Mymensingh- Halua-ghat Road.1972 - 1974 Tk. 3.00 million
22300’-0” long R.C.C. balanced cantilever Navaganga Bridge on well foundation on Jhenaidah-Kushtia Road.1967 - 1969 Tk. 8.00 million
23800’-0” long balanced R.C.C Bridge on well and pile foundation at Patkil-ghata on Khulna-Satkhira Road.1966 - 1967 Tk. 15.00 million