SL No | Name of the Contract | Period | Completed Value |
---|---|---|---|
1 | Construction of Purbachal Link Road from Kanchan Bridge to Balu River Bridge Approach (Chainage 0+000 km to 6+380 km), (Package No. 01, Lot No. 01) under RAJUK. | Jul 11 - Mar 14 | Tk. 1975.58 million |
2 | Periodic Maintenance Program - 2008 -2009, Contract No. PMP-09/Overlay(1st Tranche). | Apr 09 - Mar 11 | Tk. 290.30 million US $ 4.21 million |
3 | Periodic Maintenance Programme-2008-2009, Contract No. PMP-24/Overlay (2nd Tranche). | Apr 09 - Jun 10 | Tk. 188.42 million US $ 2.73 million |
4 | Periodic Road Maintenance Programme 2005-2009, PMP. Contract No. 17/DSST & Overlay (2nd Tranche). | Apr 09 - Mar 10 | Tk. 134.80 million |
5 | Periodic Road Maintenance Component under Road Network Improvement & Maintenance Project – II, Contract No.PRMC – RZ – 5. | Jan 08 - Apr 09 | Tk. 100.81 million US $ 1.44 million |
6 | Periodic Road Maintenance Component under Road Network Improvement & Maintenance Project – II, Contract No.PRMC – RZ – 6. | Jan 08 - Apr 09 | Tk. 88.51 million US $ 1.26 million |
7 | Maintenance of National Highway N1 Road Section from End of Comilla Bypass to Start of Feni Bypass (34.62 km) under Road Maintenance and Improvement Project. | Jun 05 - Apr 07 | Tk. 348.521 million US $ 5.89 million |
8 | Periodic Maintenance Program – 2005 – 2006, Contract No. PMP 2005 - 2006/02 | Nov 05 - Apr 06 | Tk. 120.91 million US $ 1.86 million |
9 | Improvement of Zakigonj-Vingar- bazar- Laxmibazar-Dubagbazar Road, Contract Package No.Syl/UZR-52. | Dec 04 - Jun 05 | Tk. 110.442 million US $ 1.84 million |
10 | Periodic Maintenance Program - 2004- 2005 Contract No. PMP 2004-2005/10 | Dec 04 - Jun 05 | Tk. 110.442 million US $ 1.84 million |
11 | Improvement of Feeder Roads Type - A under RRMP-III, Contract No – F-26 | Aug 02 - Feb 05 | Tk. 177.47 million US$ 3.09 million |
12 | Periodic maintenance works on (i) Begumgonj-Dhagonbhuiyan-Feni Road (Ch: 21+000 - 36+000) and (ii) Bashurhat (Companygonj) -Dhagonbhuiyan Road (Ch : 0+000 - 9+000) under Contract no. PMP-2003 - 2004/06 | Jan 04 - Jun 04 | Tk. 66.455 million US$ 1.11 million |
13 | Periodic maintenance works on Dhaka-Chittagong National Highway Ch: 23+000 - 60+500 (at different points) under Contract no. PMP-2003 - 2004/15 | Jan 04 - Jun 04 | Tk. 35.982 million US$ 0.60 million |
14 | Periodic maintenance works on Mainamati - Brahmanbaria and Biroti - Showagonj Road under Contract no. PMP-2002/05 (Comilla Zone -I) | May 03 - Feb 04 | Tk. 74.695 million US$ 1.29 million |
15 | Periodic maintenance works on Kamarkhali - Magura - Jhenaidah Road under Contract no. PMP/2001/04(Khulna -II) | June 01 - Mar 02 | Tk. 83.59 million US$ 1.47 million |
16 | Construction and Reconstruction of 18.838 k.m. Road from Baraierhat to Wahedpur on Dhaka-Chittagong Highway, Contract-8, Jamuna Bridge Access Roads Project (ADB Project). | Dec. 98 - Jun 2001 | Tk. 626.858 million US$ 14.71 million |
17 | Second Road Rehabilitation & Maintenance Project, 3rd year Programme, Periodic Maintenance, Contract–P16 (Khulna-Noapara-Bagerhat-Pirojpur-Togra Road) IDA Project. | Mar 98 - Aug 99 | Tk. 213.669million US$ 5.067 million |
18 | Second Road Rehabilitation and Maintenance Project, Widening Contract -W3 (Chuknagar – Satkhira- 30km) IDA Project. | Jan 97 - Aug 99 | Tk. 401.305 million US$ 10.45 million |
19 | Second Road Rehabilitation and Maintenance Project, Contract P- 1, (Jhenaidah - Jessore – Khulna - 108 k.m.) Overlay including improvement of Some Portion, (IDA Project). | May 94 - Dec 95 | Tk. 470.75 million US$ 11.843 million |
20 | Feeder Roads Improvement Project, Contract - 9, (Porabari – Gopalpur, Feeder Road - 7.60 k.m.) ADB Project. | Nov 92 - Nov 94 | Tk. 114.187 million US$ 3.471 million |
21 | Road Improvement Project, Contract -13. A portion of Feni - Chittagong National Highway 11.14 k.m. (ADB Project). | Jan 90 - Nov '92 | Tk. 238.436 million US $ 7.569 million |
22 | Widening & Overlay of Tongi - Joydevpur - Bhaluka Road, A Portion of Dhaka - Mymensingh National Highway. | Aug 88 - Mar 90 | Tk. 35.00 million Tk. 35.00 million |
23 | Feni-By-Pass Road (Gr.-II & Gr.-III) Overlay and strengthening of the Pavement (IDA Project). | Jun 84 - Mar 86 | Tk. 130.00 million |
24 | Improvement of Mymensingh - Madhupur Road - A Portion of Mymensingh - Tangail Road. | Dec 80 - Mar 82 | Tk. 16.15 million |
25 | Improvement of Mymensingh - Haluaghat Road (Group I & III) | Dec 78 - May 80 | Tk. 18.00 million |